The Cavalier Daily
Serving the University Community Since 1890

Goodwin (Emmet Street) Bridge

$3.35 million structure bridging the busy Emmet Street corridor between University Hall and the Lambeth Field Apartments.

Project Start: March 2003

What's Done: Bridge is currently open for use with all bridge and approach pathwork completed.

In Progress: Construction of fencing and the installation of landscaping along the bridge's Lambeth Field approach.

What's Next: Painting touch-up, erection of fencing and some additional planting of grass and small shrubs.

Estimated Completion Date: February 2005

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

In this episode of On Record, we hear from Dr. Amanda Lloyd, director of the Virginia Prison Education Program, which offers Virginia’s first bachelor’s degrees to incarcerated individuals. Dr. Lloyd discusses how and why the University chose her to lead this historic initiative.