Goodwin (Emmet Street) Bridge

$3.35 million structure bridging the busy Emmet Street corridor between University Hall and the Lambeth Field Apartments.

Project Start: March 2003

What's Done: Bridge is currently open for use with all bridge and approach pathwork completed.

In Progress: Construction of fencing and the installation of landscaping along the bridge's Lambeth Field approach.

What's Next: Painting touch-up, erection of fencing and some additional planting of grass and small shrubs.

Estimated Completion Date: February 2005