$129.8 million basketball arena that will contain 15,000 seats and a 1,500 car parking garage.

Project Start: April 2003

What's Done: Restoration of Emmet Street Dell area, major structural work on the parking garage and arena, as well as a significant amount of mechanical, electrical and plumbing rough-in work.

In Progress: Arena's roofing structure, placing of concrete block wells and a mechanically-stabilized earth-retaining wall in front of the arena's main entrance, in addition to continued mechanical, electrical and plumbing installations.

What's Next: Completion of arena roof and a trasnsition structure from the arena to yet-to-be built practice courts.

Estimated Completion Date: June 2006

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

Co-president Armelle Worrel gives a behind-the-scenes look at U.Va.’s club pickleball team, highlighting the welcoming culture, national championship success, what it’s like to lead such a large team, and partnerships and sponsorships that help the program thrive. This episode explores what makes UVA pickleball a trailblazer and a vibrant part of student life on Grounds.