John Paul Jones Arena & Dell Work

$129.8 million basketball arena that will contain 15,000 seats and a 1,500 car parking garage.

Project Start: April 2003

What's Done: Restoration of Emmet Street Dell area, major structural work on the parking garage and arena, as well as a significant amount of mechanical, electrical and plumbing rough-in work.

In Progress: Arena's roofing structure, placing of concrete block wells and a mechanically-stabilized earth-retaining wall in front of the arena's main entrance, in addition to continued mechanical, electrical and plumbing installations.

What's Next: Completion of arena roof and a trasnsition structure from the arena to yet-to-be built practice courts.

Estimated Completion Date: June 2006

Local Savings

Puzzles
Hoos Spelling
Latest Video

Latest Podcast

Since the Contemplative Commons opening April 4, the building has hosted events for the University community. Sam Cole, Commons’ Assistant Director of Student Engagement, discusses how the Contemplative Sciences Center is molding itself to meet students’ needs and provide a wide range of opportunities for students to discover contemplative practices that can help them thrive at the University.