Rouss Hall

$43 million project to renovate Rouss Hall and construct an 115,000 square foot addition for the Commerce School.

Project Start: January 2005

What's Done: Work on Varsity Hall and Hospital Drive to accommodate Varsity Hall's relocation opposite East Range.

In Progress: Shoring up of Varsity Hall structure for move.

What's Next: Relocation of Varsity Hall in April, interior demolition and asbestos removal in Rouss Hall.

Estimated Completion Date: July 2007

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

Co-president Armelle Worrel gives a behind-the-scenes look at U.Va.’s club pickleball team, highlighting the welcoming culture, national championship success, what it’s like to lead such a large team, and partnerships and sponsorships that help the program thrive. This episode explores what makes UVA pickleball a trailblazer and a vibrant part of student life on Grounds.