$38.9 million project to house the Engineering School's Material Science department and Center for Nanoscopic Materials Design.

Project Start: February2003

What's Done: Underground utilities relocated, site excavation completed.

In Progress: Laying concrete foundations.

What's Next: Continue foundation work, installation of structural steel.

Estimated Completion Date:

September 2006

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

Co-president Armelle Worrel gives a behind-the-scenes look at U.Va.’s club pickleball team, highlighting the welcoming culture, national championship success, what it’s like to lead such a large team, and partnerships and sponsorships that help the program thrive. This episode explores what makes UVA pickleball a trailblazer and a vibrant part of student life on Grounds.