The Cavalier Daily
Serving the University Community Since 1890

John Paul Jones Arena & Dell Work

Estimated reading time: 0 minutes

$129.8 million basketball arena that will contain 15,000 seats and a 1,500 car parking garage.

Project Start: April 2003

What's Done: Restoration of Emmet Street Dell area, major structural work on the parking garage and arena, as well as a significant amount of mechanical, electrical and plumbing rough-in work.

In Progress: Arena's roofing structure, placing of concrete block wells and a mechanically-stabilized earth-retaining wall in front of the arena's main entrance, in addition to continued mechanical, electrical and plumbing installations.

What's Next: Completion of arena roof and a trasnsition structure from the arena to yet-to-be built practice courts.

Estimated Completion Date: June 2006

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

In this episode of On Record, Professor Ran Zhao, a Chinese professor and director of U.Va. in Shanghai, highlights how the program empowers students to immerse themselves in Chinese language and culture with intensive instruction and fun opportunities to explore the city. After all, learning a language means experiencing its culture firsthand.